Latest updates for Namma Metro:
1. The newly inaugurated Reach 2, on Nov 11, 2015 will be shut down till Dec 12th and will be operational from 9am to 7pm from Dec 13th to Dec 20th to facilitate integration of the signalling system for the underground portion EW with the above ground portions of Reaches 1 ( Bypanahalli to MG Rd.) and Reach 2(Magadi Rd to Mysore Rd.) which are operational.
2. Bangalore metro is trying to operationalize the entire EW portion by end January. This is optimistic. Currently derailment coefficient tests are going on in the UG portions EW. Following that there will be tests of the signals and communication systems that will last more than a month even 2 months according to the MD, Namma Metro.
These current tests entailing the measurement of derailment coefficients are being monitored by RDSO and some French experts. Following this and post signals integration and tests, the CRS will have to certify and so one hopes commercial operations begin by March.
3. The EW trains when running will NOT stop at the Majestic interchange which connects the NS and EW lines.
This nodal station which is UG is incomplete and will be functional when the NS lines are operational.
4. Approximately 1470m of tunneling is left NS. EW tunnels are long finished see the points 1-3 above.
Completion of 1470m of tunneling will finish all tunneling activities in Phase 1.
5. As a poster has pointed out cracks developed in buildings above TBM Kaveri. This TBM has halted so that individuals can vacate buildings that may collapse. Kaveri was to have started to move last Tuesday. Kaveri has tunneled 539m and 208m is left for breakthrough at Majestic. This will end its job for Phase 1.
6. TBM Krishna tunneling parallel to Kaveri has yet to start its drive of 747m from Chikpet station to Majestic. Most likely it will start Dec 13th. It is undergoing refurbishment of its cutters at Chikpet station.
This TBM is the one that will delay the project. Like Kaveri it will tunnel parallel to it and under decrepit buildings in the densely populated Chikpet area and so will have to proceed slowly. Like Kaveri there is the possibility of buildings above it caving in, developing cracks etc.
7. TBM Margarita has finished tunneling 973m from Majestic to North ramp at Mantri Mall/Sampige rd. Grouting operations are being carried out on the finished tunnel. Preparations are also being made to pour concrete to prepare the bed to lay the tracks in the finished tunnel. This is the longest tunnel in Phase 1 of NM.
8. TBM Godavari that was dormant for a year due to a broken cutter head, has now tunneled 461m parallel to Margarita from Sampige Rd/Mantri Mall towards Majestic. It needs to tunnel 512m more and be done for Phase 1.
9. Tunneling for Godavari will be substantially easier once it tunnels 110m more as it has gone past already the dense granite strata that broke its cutter head which was partly inexperienced contractors. It should breakthrough at Majestic in about 5 months.
10. All above ground reaches are essentially complete. Reaches 1,2,3 are commercially operational. Reach 4 is essentially ready but cut-off from the NS depot at Peenya since the UG portion of NS is incomplete. Plans by BMRC to hoist trainsets on Reach 4 and operate Reach 4 as a separate entity have been dropped. So the above ground Reach 4( Banashankari to Chikpet-Majestic) will be operational once NS UG is ready.
11. I have seen many of the Metro stations up close in the last weeks, on the way to work. The construction is shoddy. Thought has not gone into the stations. Absence of service roads creates severe and serious traffic bottlenecks. Access to the stations in some places is difficult. At one station on Reach 3, people have to cross a busy National highway(Tumkur rd.) making such a journey hazardous. Some panels of the station have not been affixed, perhaps at some future time there will be a overbridge connecting to the station at the missing panels. Paint is already gone and signage has letters missing a year into operations. Fancy art work has paint running off and construction debris still lies around in operational sections. Rivets at the joints connecting roof panels have given way, perhaps leading to leaky roofs that were reported during rain showers at stations esp. in Reach 3.
http://www.newindianexpress.com/cities/ ... 120383.ece
The MD Namma Metro also looks after the Tourism department for the state of Karnataka. Perhaps the powers that be should at least appoint a full time MD who can worry about this project, that is already over budget and massively late.