Tarbela Turbine Operated Despite Warning From A German Expert , Resulting In Loss Of Rs 25 Billion To The Paki Exchequer
Premature Tarbela-IV launch has cost Rs25 bn
The News International - Ansar Abbasi
Sept 5, 2018
Premature Tarbela-IV launch has cost Rs25 bn
The News International - Ansar Abbasi
Sept 5, 2018
ISLAMABAD: The premature inauguration of the 1,410MW Tarbela Dam 4th extension hydro-power project (c) in March by the Water and Power Development Authority (Wapda) has culminated in operational losses of more than Rs25 billion over the three-month annual flood season, Wapda sources and officials at the Ministry of Water Resources said.
Should not fault Immy for this !Apparently, acting under political pressure, Wapda inaugurated the $850 million Tarbela-IV project in March, despite warnings from the German engineering consultant, Voith, not to operate the turbine of the fourth tunnel at Tarbela Dam while its reservoir was at the dead level.
So, the news was suppressed until nowHowever, the Wapda went ahead and and ran the turbine for several hours during the inauguration of the project by the-then prime minister, Shahid Khaqan Abbasi. As a result, mud and slurry from the practically empty reservoir filled part of the tunnel, rendering three turbines inoperable.
Seems like the job is for a " foreign expert". Indian experts need not applyThe Wapda sources said that the draft tube connecting the turbine to the tail race channel is buried under tons of mud. All subsequent efforts by government agencies, including the Pakistan Navy, to remove the debris have failed and the three units of 1,410 MW capacity have been offline since July, during the annual filling of the Tarbela reservoir.
The Kaptaan will of course deny responsibility for this negligence . This was "before NAYA PAKISTAN"According to the sources, the power not generated resulted in lost revenue of Rs280 million a day, or Rs25.2 billion for the 90-day flood season. To date, the government is yet to order an inquiry into the Tarbela-IV debacle. However, the Ministry of Water Resources is now considering to constitute an investigation committee to ascertain responsibility, a spokesman told The News.
Multiply this kind of sheer negligence by a hundred similar cases and you see why Pakiland is in a financial shit holeSince the Tarbela Dam reservoir was at the dead storage level in March, the only little water available for use during the inauguration ceremony was located in the flushing inlet and full of silt. “The result is before us now -- a daily loss of Rs280 million,” the source said.
The sources said that the scale of the repair work on Tarbela-IV was so great that the entire current flood season has been lost. Wapda would need to construct a temporary downstream coffer dam and then drain the area between the draft tube and coffer dam so that cranes and earth moving equipment could remove tons of debris and reach the embedded draft tubes. If the draft tubes are found damaged, as is apprehended, further costs would be incurred, the sources said.
Guess no one had the guts to tell the then Paki PM that it was a premature inauguration . He had his five minutes of "glory" and the results are there for all to seeBy adopting the best engineering practices and undertaking heroic efforts, Wapda engineers, consultants and contractors managed to clear the gate of Unit 16 by Tuesday evening. Ongoing work on the other gates would likely take another 48 to 72 hours. This would lead to commencement of power generation from Tarbela-IV.