^^^ 1. DFFCIL have ceased updating trimonthly progress and have now become silent for close to a year, no updates.
2. Suddenly in Dec 2018 they brought out what they called Volume 1 of a journal where in the opening pages (in fact page 2) they gave timelines where the DFC, both Eastern and Western arms except the WB section was to be finished by March 2020.
3. Now within 5 months of publication of this "journal", they meaning DFCC have tweeted completion dates and time lines that project completion in Dec 2021. I mean within 5-6 months how can completion go back by 2 years. Why wait for the election to be over to make this announcement?
4. On sections claimed to be completed in Dec 2018, one has videos from Jan 2019, and March 2019, showing incomplete loop lines, OHE work pending, no wiring for sure but also missing poles.
5. Sections where completion dates were announced within a month in the Goyal presser now are tweeted by DFC themselves to be completed in 1.5 years. This is total nonsense.
6. Google Earth shows work is way behind schedule on major bridges.
If people are gaga with this Goyal, good luck to you. He seems to me quite unprofessional with no control on his ministry.
Since I have made these claims based on official announcements from the ministry, here are the links:
The journal I refer to, pl. take a look at page 2 where timelines are announced all by March 2020 for project completion(note Journal comes out Dec 2018):
http://www.iricen.gov.in/iricen/journal ... EC2018.pdf
Note the tweets a few days ago after the elections pushing completion now to Dec 2021, if that is the delay how come it was not known 5 months ago? This is a significant delay in the project from March 2020 to Dec 2021:
https://pbs.twimg.com/media/D79UuTlUcAATsj-.jpg
https://pbs.twimg.com/media/D79DB55UIAA_sxb.jpg
Notice the first two items in the journal in Dec 2018, listing two sections as completed 194 km Khurja-Bhadan on EDFC and Ateli-Madar on WDFC as completed. Now the tweets AFTER the election just say trial run so the completed sections were not completed after all and the public was misled prior to the election. I am using official documents only.
Now the videos, one near Daud Khan (Aligarh) (video posted Jan 24, 2019) on the so-called completed section of EDFC, Khurja-Bhadan, note incomplete loop lines and OHE and another video near Khurja ( video posted March 2019) on EDFC same story, all videos in Jan 2019 and March 2019, well after the Dec 2018 publication date of the DFCCIL journal.
https://www.youtube.com/watch?v=itCBfpPIIGs
This video posted in March 2019, shows even the OHE poles all skewed and not even fixed leave alone wiring, yet Khurja-Bhadan is listed as complete in Dec 2018 in the journal ^^^
https://www.youtube.com/watch?v=oaz5XbL0Z54