Just when I thought that FINALLY Tata Projects had gotten their act together on the much delayed 102km WDFC section from Vaitarna to JNPT, disaster has again struck, with poor project management. I am not sure what ails this Tata Company. 14 pillars of a ramp connecting WDFC to IR at Kharbao where the deck slab had also been put in, have been razed. Tata Construction refers all queries to DFCCIL which remains tight lipped.
https://twitter.com/i/status/1925884009109655572
https://timesofindia.indiatimes.com/cit ... 472851.cms
Two major elements of the WDFC were completed in recent weeks giving me hope that the last 102km section would be completed by Dec 2025 after numerous deadlines being missed including April 2025.
1. The Kundevahal tunnel near JNPT is now through, the last tunnel on the WDFC to be completed. Tunneling has to be large enough to carry double stack container freight and both the double lines are in a single tube.
2. A massive 110m, 1500 tonne steel girder bridge was launched over CR tracks at Panvel to carry twin WDFC tracks from JNPT over CR tracks and make the alignment go from left to right looking towards Vaitarna.
It is now a question of earthwork, and track laying and systems and signalling. All of this will slow down for 3 months due to monsoon.
%%%%%%%%%%%%%%%%%%
The last three block section are nearing completion for doubling on the Miraj Pune line, thus comleting Bangalore to Pune doubling and FEDL. The difficult one is Shindwane ghat with extremely tall viaducts which will complete first by late July and then 20+km Targaon--Rahimatpur--Koregaon which is flat but was delayed massively due to LA court cases.
Mid May(Shindwane ghat only)
https://www.youtube.com/watch?v=ihAhdeTV_UY
A more recent view 2 days old : (Sindwane ghat + Targaon to Rahimatpur)
https://www.youtube.com/watch?v=-Y86P7IUzFk
Targaon---Rahimatpur in mid May
https://www.youtube.com/watch?v=Dny6HkcVZ6E
SWR has long delayed the electrification of the Mangalore to Bangalore section. Some whip has been cracked and the last remaining 32km in the ghats where work was crawling is finally being pushed with a near traffic block till Nov 1. Part of the problem is that access to the track is impossible by truck and trains are needed. Plus work has to be done in many tunnels of installing brackets and then wiring. There is freight too and the monsoons plus the poor project management of SWR which is legendary are all impediments. A recent view of RE on the Saklespur to Subrahmanya road section. Only a 32 km section left, 23 km done. Rest all done between Bangalore and Mangalore of RE.
https://www.youtube.com/watch?v=TmdL56PnNcE